Following are notifications of upcoming shutdowns:

Building:       E23, central lobby, floors 1 - 4
System:         Chilled water system for air handler 9
Date:           1/24/96
Day:            Wednesday
Time:           7:30 a.m. - 1 p.m.
Duration:       5 1/2 hours
Reason:         To replace butterfly valve for air handler 9 chilled
                water coils
Effect:         Loss of chilled water systems to the above area and
                system
                for the duration of the shutdown

Building:       E40, air handler 1
System:         ventilation and air supply
Date:           1/26/96
Time:           1 p.m. - 1:30 p.m.
Duration:       1/2 hour
Reason:         To change filters in vent
Effect:         Minimal effect on building's air supply and ventilation