[31668] in Hotline Meeting
Bldg. 2 shutdown
daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Fri Jan 19 08:27:43 1996
Date: Fri, 19 Jan 1996 08:28 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, cappucci@MIT.EDU, dcarlson@MIT.EDU, opsnote@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, opsnote@mit.edu,
sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"cappucci@mit.edu",
IN%"dcarlson@mit.edu",IN%"opsnote@mit.edu"
Following are notifications of upcoming shutdowns:
Building: 2 (see below for more complete details)
System: Electric power and lighting
Date: 1/27/96
Day: Saturday
Time: 7 a.m. - 7 p.m.
Duration: 12 hours
Reason: To replace a circuit breaker panel on the third floor
Effect: Loss of building power/lights to the southern section
of Bldg. 2 (the side facing Memorial Drive) starting
at -052, -146, -246, -348 for the duration of the shutdown.