[31624] in Hotline Meeting
Bldgs 3, 8, and 68 shutdowns
daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Tue Jan 16 11:12:56 1996
Date: Tue, 16 Jan 1996 11:13 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"dcarlson@mit.edu", IN%"cappucci@mit.edu"
Following are notifications of upcoming shutdowns:
Building: 3 and 8
System: 3 - electric power and lighting; 8 - 480 volt lab power
ONLY
Date: 1/20/96
Day: Saturday
Time: 7 a.m. - 3 p.m.
Duration: 8 hours
Reason: To replace faulty 2400 volt primary power cable
Effect: Loss of power and air supply systems (ventilation,
cooling, exhaust; lab exhaust, general exhaust,
toilet exhaust) to building 3; loss of 480v lab power
to building 8
Building: 68
System: Medium pressure steam, fire alarm and smoke detectors
Date: 1/18/96
Day: Thursday
Time: 3 p.m. - 11 p.m.
Duration: 8 hours
Reason: To repair leak on main supply to cage washer
Effect: Loss of medium pressure steam, fire alarm and smoke
detector systems for the duration