Bldg. 31 shutdown

daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Fri Jan 12 14:41:51 1996

Date: Fri, 12 Jan 1996 14:42 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, cappucci@MIT.EDU, dcarlson@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
 shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"cappucci@mit.edu", IN%"dcarlson@mit.edu"

Following are notifications of upcoming shutdowns:

Building:       31
System:         Low pressure steam (building heat)
Date:           1/16/96
Day:            Tuesday
Time:           7:30 a.m. - 11:30 a.m.
Duration:       4 hours
Reason:         Steam lines need to be relocated to allow for
                installation of new fume hood
Effect:         Loss of low pressure steam system for the duration of
                the shutdown

*** Please note that if temperatures are severe (i.e., less than 20
    degrees Fahrenheit) on Tuesday, the shutdown will be rescheduled to
    a later date.