Bldg. 31 shutdown

daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Fri Jan 5 14:57:15 1996

Date: Fri, 5 Jan 1996 14:58 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
 shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"dcarlson@mit.edu", IN%"cappucci@mit.edu"

Building:       31
System:         Medium pressure steam system
Date:           1/8/96
Day:            Monday
Time:           7:30 a.m. - 11:30 a.m.
Duration:       4 hours
Reason:         Relocation of lines in order to install a new fume hood
Effect:         Loss of medium steam pressure systems for the duration
                of the shutdown