Bldg. 31 shutdown
daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Fri Jan 5 14:57:15 1996
Date: Fri, 5 Jan 1996 14:58 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu", IN%"dcarlson@mit.edu", IN%"cappucci@mit.edu"
Building: 31
System: Medium pressure steam system
Date: 1/8/96
Day: Monday
Time: 7:30 a.m. - 11:30 a.m.
Duration: 4 hours
Reason: Relocation of lines in order to install a new fume hood
Effect: Loss of medium steam pressure systems for the duration