SHUTDOWNS

daemon@ATHENA.MIT.EDU (Michael Smith)
Tue Oct 10 10:53:53 1995

Date: Tue, 10 Oct 1995 10:52 EDT
From: Michael Smith <MSMITH%MITPPL.bitnet@mitvma.mit.edu>
To: SHUTDOWNS@MIT.EDU, OPSNOTE@MIT.EDU
X-Envelope-To: OPSNOTE@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To: IN%"SHUTDOWNS@MIT.EDU",IN%"OPSNOTE@MIT.EDU"

From:   PPL::MFILES       10-OCT-1995 10:37:55.74
To:     MSMITH
CC:     MFILES
Subj:   shutdowns

From:   IN%"MSMITH%MITPPL.bitnet@mitvma.mit.edu"  "Michael Smith" 10-OCT-1995 10
   :20:37.28
To:     IN%"PLANT-SHUTDOWN@MIT.EDU", IN%"DCARLSON@MIT.EDU", IN%"CAPPUCCI@MIT.EDU
   "
CC:     IN%"SDVERIFY@MIT.EDU"
Subj:   SHUTDOWNS




BUILDING:               W33,W16,W51,W53,W7,W8,W4,W5,W2A,W13,W15,41,41A
                        35-WIND TUNNEL,31-WEST SIDE & 31-159 AND FRAT
                        HOUSE AT 403 MEM. DRIVE
SYSTEM:                 ALL ELECTRIC POWER & LIGHTING
DATE:                   10-12-95
DAY:                    THURSDAY
TIME:                   6:30 A.M. - 6:35 A.M.
DURATION:               LESS THAN 2 MINUTES
REASON:                 TO WORK ON 2400 VOLT LOOP
EFFECT:                 ALL POWER & LIGHTING (EXCEPT EMERGENCY POWER)


BUILDING:               E19 6TH & 7TH FLOORS
SYSTEM:                 AH7-1 RF & AH7-1 SF
DATE:                   10-13-95 - 10-16-95
DAY:                    FRIDAY - MONDAY
TIME:                   5:00 P.M. - 7:00 A.M.
DURATION:               62 HOURS
REASON:                 WORK ON DISTRIBUTION DUCT
EFFECT:                 SUPPLY-VENTILATION