BUILDING:       20
SYSTEM:         NORMAL POWER & LIGHTING (WINGS A & B 2ND FL ONLY)
                EMERGENCY POWER
DATE:           10/5/95
DAY:            THURSDAY
TIME:           6:30 - 7:30 AM
DURATION:       1 HOUR
REASON:         TO RECONNECT LAB PANELS TO NORMAL POWER
EFFECT:         NO EMERGENCY POWER FOR THE ENTIRE BUILDING, NO NORMAL
                POWER FOR AREAS MENTIONED ABOVE