SHUTDOWNS

daemon@ATHENA.MIT.EDU (Michael Smith)
Tue Sep 19 10:03:59 1995

Date: Tue, 19 Sep 1995 10:00 EDT
From: Michael Smith <MSMITH%MITPPL.bitnet@mitvma.mit.edu>
To: SHUTDOWNS@MIT.EDU, OPSNOTE@MIT.EDU
X-Envelope-To: OPSNOTE@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To: IN%"SHUTDOWNS@MIT.EDU",IN%"OPSNOTE@MIT.EDU"

From:   PPL::MSMITH       "Michael Smith" 19-SEP-1995 09:23:15.61
To:     IN%"PLANT-SHUTDOWN@MIT.EDU",IN%"DCARLSON@MIT.EDU",IN%"CAPPUCCI@MIT.EDU"
CC:     IN%"SDVERIFY@MIT.EDU",MSMITH
Subj:   SHUTDOWNS

ROUTINE
BUILDING:               W20-575A
SYSTEM:                 ATHENA COOLING UNIT
DATE:                   9-25-95
DAY:                    MONDAY
TIME:                   9:00 A.M. - 12:00 P.M.
DURATION:               3 HOURS
REASON:                 REPAIR SHEAVES ON FAN
EFFECT:                 SUPPLY-COOLING

ROUTINE
BUILDING:               NW12 - VARIOUS ROOMS 1ST 2ND AND 3RD FLOORS
SYSTEM:                 EXHAUST,GENERAL,TOILET, & FAN COIL UNITS
DATE:                   9-26-95
DAY:                    TUESDAY
TIME:                   7:30 A.M. - 7:30 P.M.
DURATION:               12 HOURS
REASON:                 P.M.'S
EFFECT:                 SUPPLY - COOLING & HEATING,
                        EXHAUST - LABORATORY, GENERAL & TOILET

CRITICAL**
BUILDING:               NW61
SYSTEM:                 LOW PRESSURE STEAM
DATE:                   9-19-95
DAY:                    TUESDAY
TIME:                   12:00 P.M. - 4:00 P.M.
DURATION:               4 HOURS
REASON:                 REPLACE VALVE
EFFECT:                 HEATING

CRITICAL**
BUILDING:               24
SYSTEM:                 CHILLED WATER
DATE:                   9-21-95
DAY:                    THURSDAY
TIME:                   7:30 A.M. - 9:30 A.M.
DURATION:               2 HOURS
REASON:                 REPAIR LEAK
EFFECT:                 COOLING