SHUTDOWNS
daemon@ATHENA.MIT.EDU (CVENEZIA%MITPPL.bitnet@mitvma.mit.)
Wed Aug 2 19:10:06 1995
Date: Wed, 2 Aug 1995 19:05 EDT
From: CVENEZIA%MITPPL.bitnet@mitvma.mit.edu
To: DCARLSON@MIT.EDU, CAPPUCCI@MIT.EDU, SHUTDOWNS@MIT.EDU, SDVERIFY@MIT.EDU,
OPSNOTE@MIT.EDU
X-Envelope-To: CAPPUCCI@MIT.EDU, DCARLSON@MIT.EDU, OPSNOTE@MIT.EDU,
SDVERIFY@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To:
IN%"DCARLSON@MIT.EDU",IN%"CAPPUCCI@MIT.EDU",IN%"SHUTDOWNS@MIT.EDU",IN%"SDVERIFY
@MIT.EDU",IN%"OPSNOTE@MIT.EDU"
ROUTINE SHUTDOWNS
BUILDINGS: 3 (NORTH AND SOUTH WING)
1 (ENTIRE BUILDING)
SYSTEM: ELECTRIC POWER AND LIGHTING
DATE: 08-11-95 UNTIL 08-13-95
DAY: FRIDAY, SATURDAY AND SUNDAY
TIME: 7PM FRIDAY EVENING UNTIL MIDNIGHT SUNDAY
DURATION: 53 HOURS
REASON: CONSTRUCTION
EFFECT: BUILDING 3, NORTH AND SOUTH WINGS WILL HAVE NO POWER.
ALL POWER AND LIGHTING IN BUILDING 1. EMERGENCY POWER
WILL REMAIN ON (SOME LIGHTING, EXIT SIGNS, ETC...)
THERE WILL BE NO ELEVATORS, COMPUTERS,
CHILLED WATER (COOLING), VENTILATION OR EXHAUST.
*THIS NEXT SHUTDOWN IS FOR TWO CONSECUTIVE SATURDAYS 08-12-95 AND
08-19-95*
BUILDINGS: 1, 3 AND 8
SYSTEMS: ELECTRIC POWER, LIGHTING AND 480 VOLT LAB POWER
DATE: 08-12-95
DAY: SATURDAY
TIME: 7AM UNTIL 11PM
DURATION: 16 HOURS
REASON: CONSTRUCTION
EFFECT: ALL POWER AND LIGHTING IN BUILDINGS 1 AND 3. INCLUDES
ALL MECHANICAL EQUIPMENT. ELEVATORS, COMPUTERS,
CHILLED WATER (AC COOING), SUPPLY VENTILATION AND
EXHAUST WILL ALL BE AFFECTED. NOTE ON THE ABOVE TWO
SHUTDOWNS THAT BUILDING 1 WILL BE DOWN ALL WEEKEND
(8/11 - 08/13) AND BUILDING 3 (NORTH AND SOUTH WINGS).
ALL OF BUILDING 3 WILL BE DOWN ON SATURDAY 8/12 FROM
7AM-11PM. BUILDING 8 (480 VOLT LAB POWER) WILL ALSO BE
DOWN ON SATURDAY FROM 7AM-11PM.
ROUTINE
BUILDINGS: 11 AND 3
SYSTEMS: ALL ELECTRIC POWER AND LIGHTING
DATE: 08-11-95 UNTIL 08-12-95
DAY: FRIDAY AND SATURDAY
TIME: 7PM FRIDAY UNTIL 7AM SATURDAY
DURATION: 12 HOURS
REASON: CONSTRUCTION
EFFECT: ALL POWER IN THE BASEMENT OF BUILDING 11, INCLUDING
LIGHTS ONLY ON THE 2ND AND 3RD FLOORS. ALL POWER IN
MAIN CORRIDOR WING OF BUILDING 3. ALL POWER INCLUDES
ACCESS CONTROLS, ELEVATORS, COMPUTERS, LIGHTING,
CHILLED WATER (AC COOLING), SUPPLY VENTILATION AND
EXHAUST.
I APOLOGIZE FOR THIS CONFUSING AND LENGTHY EMAIL, IF YOU HAVE ANY
QUESTIONS PLEASE CONTACT HANS ANTONNSON AT 3-6822 OR MYSELF AT 3-1500.