[29204] in Hotline Meeting
[EP] bldg. 5 & 7 chilled
daemon@ATHENA.MIT.EDU (John J Morey)
Fri Jul 21 10:49:50 1995
To: vcrayton@MIT.EDU, sdverify@MIT.EDU
Cc: hotline@MIT.EDU
Date: Fri, 21 Jul 1995 10:49:46 EDT
From: John J Morey <jjmorey@MIT.EDU>
Hi -
This shutdown shouldn't effect any of our major clusters, so no problem.
Thanks for the notice
JJ
------- Forwarded Message
Received: from MIT.MIT.EDU by po8.MIT.EDU (5.61/4.7) id AA18973; Fri, 21 Jul 95 09:55:44 EDT
Received: from PLANT12.MIT.EDU by MIT.EDU with SMTP
id AA09420; Fri, 21 Jul 95 09:55:38 EDT
Message-Id: <9507211355.AA09420@MIT.EDU>
To: JIS@MIT.EDU, JJMOREY@MIT.EDU
Subject: Chilled Water Shutdown
Date: Fri, 21 Jul 95 09:56:19
From: vcrayton@MIT.EDU (Vaughn Crayton )
Utilities & Engineering would like to schedule a shutdown of all chilled
water to buildings 5 and 7. The shutdown is needed to tie in a new set of
chilled water pumps for building 5. We would like to schedule the shutdown
for Saturday (29 July) from 7am to 3pm. Would you please let me know if
this time is acceptable? If this time is not suitable would you give me an
eight hour window of when we could perform this shutdown.
------- End of Forwarded Message