[29170] in Hotline Meeting
CANCELLATION OF SHUTDOWN IN BUILDING 12
daemon@ATHENA.MIT.EDU (MFILES%MITPPL.bitnet@mitvma.mit.ed)
Mon Jul 17 16:23:16 1995
Date: Mon, 17 Jul 1995 16:18 EDT
From: MFILES%MITPPL.bitnet@mitvma.mit.edu
To: DCARLSON@MIT.EDU, CAPPUCCI@MIT.EDU, SHUTDOWNS@MIT.EDU, OPSNOTE@MIT.EDU
Cc: SDVERIFY@MIT.EDU
X-Envelope-To: CAPPUCCI@MIT.EDU, DCARLSON@MIT.EDU, OPSNOTE@MIT.EDU,
SDVERIFY@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To:
IN%"DCARLSON@MIT.EDU",IN%"CAPPUCCI@MIT.EDU",IN%"SHUTDOWNS@MIT.EDU",IN%"OPSNOTE@
MIT.EDU"
THE FOLLOWING SHUTDOWN HAS BEEN CANCELLED:
BUILDING: 12
SYSTEM: ELECTRIC POWER
DATE: 7/18/95
DAY: TUESDAY
TIME: 7:00 AM - 3:00 PM
DURATION: 8 HOURS
REASON: TO REMOVE EXISTING PANEL AND INSTALL
NEW ELECTRIC PANEL
EFFECT: NO ELECTRICAL POWER TO THE 1ST FLOOR
AND MECHANICAL PENTHOUSE AREA.
******************************************************************************
THIS SHUTDOWN WILL BE RESCHEDULED FOR A FUTURE DATE.