Following are two shutdown notifications:
Routine
Building: 3
System: Chilled water
Date: 7/12/95
Day: Wednesday
Time: 5:30 a.m. - 10:00 a.m.
Duration: 4.5 hours
Reason: Renovation
Effect: No chilled water cooling to rooms 016,
132, 134, 136, 138, 140, 144, 146, 148
for 4.5 hours
Routine
Building: NW21
System: Air handler 1, chilled water
Date: 7/21/95
Day: Friday
Time: 12:00 midnight Thurs. - 3:00 p.m. Fri.
Duration: 15 hours (or more)
Reason: Replace chilled water coils
Effect: No chilled water cooling to west side
of bldg. for 15 hours (or more)