Shutdown bldgs. 3, NW21

daemon@ATHENA.MIT.EDU (Jason M. Roush)
Tue Jul 11 12:43:59 1995

Date: Tue, 11 Jul 1995 12:40 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, shutdowns@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
 shutdowns@mit.edu
X-Vms-To: IN%"dcarlson@mit.edu",IN%"cappucci@mit.edu",IN%"shutdowns@mit.edu"

Following are two shutdown notifications:

Routine

        Building:               3
        System:                 Chilled water
        Date:                   7/12/95
        Day:                    Wednesday
        Time:                   5:30 a.m. - 10:00 a.m.
        Duration:               4.5 hours
        Reason:                 Renovation
        Effect:                 No chilled water cooling to rooms 016,
                                132, 134, 136, 138, 140, 144, 146, 148
                                for 4.5 hours


Routine

        Building:               NW21
        System:                 Air handler 1, chilled water
        Date:                   7/21/95
        Day:                    Friday
        Time:                   12:00 midnight Thurs. - 3:00 p.m. Fri.
        Duration:               15 hours (or more)
        Reason:                 Replace chilled water coils
        Effect:                 No chilled water cooling to west side
                                of bldg. for 15 hours (or more)