Shutdown bldg. 68

daemon@ATHENA.MIT.EDU (Jason M. Roush)
Mon Jul 10 11:20:04 1995

Date: Mon, 10 Jul 1995 11:16 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"

Following is a shutdown notification:

Routine

        Building:               68
        System:                 Electrical power and lighting
        Date:                   7/27/95
        Day:                    Thursday
        Time:                   6:00 a.m. - 6:00 p.m.
        Duration:               12 hours
        Reason:                 Testing
        Effect:                 Entire bldg. will lose power and
                                lighting for only a few hour in a.m.
                                After that time, short outages of
                                2 hours or less with occur in various
                                locations throughout bldg.