We just received new information on the bldg. 12 electrical shutdown
scheduled for Weds. July 5th from 7:00 a.m. - 3:00 p.m. The electrical
power will in fact NOT be turned off, and only the duct smoke detectors
will be affected.
Sorry for any inconvenience.