[28817] in Hotline Meeting
Shutdown bldg. E52
daemon@ATHENA.MIT.EDU (Jason M. Roush)
Mon Jun 19 11:29:58 1995
Date: Mon, 19 Jun 1995 11:26 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"
Following is a shutdown notification:
Routine
Building: E52
System: Chilled water, domestic hot & cold water
Date: 6/22/95
Day: Thursday
Time: 11:00 p.m. (Weds.) - 7:00 a.m. (Thurs.)
Duration: 8 hours
Reason: Construction
Effect: No chilled water, domestic hot & cold
water to bldg. for 8 hours