Shutdown bldg. 7
daemon@ATHENA.MIT.EDU (Jason M. Roush)
Fri Jun 16 11:48:09 1995
Date: Fri, 16 Jun 1995 11:44 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, sdl-adm-lib@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: sdl-adm-lib@mit.edu, sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu",IN%"sdl-adm-lib@mit.edu"
Following is a shutdown notification:
Routine
Building: 7
System: Chilled water
Date: 6/22/95
Day: Thursday
Time: 7:00 a.m. - 7:00 p.m.
Duration: 12 hours
Reason: Renovations
Effect: No cooling on third floor of bldg.
for 12 hours