[28756] in Hotline Meeting
Shutdown bldgs. W20, E52, 35
daemon@ATHENA.MIT.EDU (Jason M. Roush)
Wed Jun 14 15:05:48 1995
Date: Wed, 14 Jun 1995 15:02 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"
Following are three shutdown notifications:
Routine
Building: W20-575C
System: Supply fan
Date: 6/16/95
Day: Friday
Time: 1:00 a.m. - 2:00 a.m.
Duration: 1 hour
Reason: Preventive maintenance
Effect: No cooling to W20-575C for 1 hour
Routine
Building: E52
System: Chilled water, hot water
Date: 6/19/95
Day: Monday
Time: 5:30 a.m. - 3:30 p.m.
Duration: 10 hours
Reason: Renovation
Effect: No heating or cooling in bldg. for
10 hours
Routine
Building: 35
System: Chilled water
Date: 6/20/95
Day: Tuesday
Time: 7:00 a.m. - 1:00 p.m.
Duration: 6 hours
Reason: Construction
Effect: No cooling to basement floor of bldg.
for 6 hours