[28744] in Hotline Meeting
Shutdown bldgs. E17, E18
daemon@ATHENA.MIT.EDU (Jason M. Roush)
Wed Jun 14 09:31:51 1995
Date: Wed, 14 Jun 1995 09:26 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, opsnote@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: opsnote@mit.edu, sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu",IN%"opsnote@mit.edu"
Following is a shutdown notification:
Routine
Buildings: E17, E18
System: Electrical power
Date: 6/21/95
Day: Wednesday
Time: 7:00 a.m. - 9:00 a.m.
Duration: 2 hours
Reason: Construction
Effect: Losses of electrical power, as well as
ventilation and general/lab exhaust,
for short periods of time in various
locations in bldgs. for 2 hours total