Chiller & Hot water shutdown-E52

daemon@ATHENA.MIT.EDU (Doug Goulet )
Tue Jun 13 08:09:19 1995

To: Hotline@MIT.EDU, sdverify@MIT.EDU
Cc: abarkley@MIT.EDU, faith@MIT.EDU
Date: Tue, 13 Jun 95 08:10:19
From: degoulet@MIT.EDU (Doug Goulet )

6-12-95

Physical Plant is trying to schedule a chilled and hot water shutdown in 
the basement of Building E52.  We would like to do the shutdown on Monday 
June 19.  The shutdown will start at 7:30 and will last all day (8 hours). 
This shutdown may effect all of building E52.  A shutdown of the chilled 
water will effect the air conditioners.

Please let me know if June 19 will be a problem.

Thanks-
Doug Goulet