Shutdown bldgs. 13, E23, NW22

daemon@ATHENA.MIT.EDU (JASON M. ROUSH)
Wed May 31 15:15:37 1995

Date: Wed, 31 May 1995 15:09 EDT
From: "JASON M. ROUSH" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: sdverify@MIT.EDU, shutdowns@MIT.EDU
X-Vms-To: IN%"shutdowns@MIT.EDU"

Following are four shutdown notifications:

Routine

        Building:               13
        System:                 Supply fan coil
        Date:                   6/5/95
        Day:                    Monday
        Time:                   5:00 p.m. - 10:00 p.m.
        Duration:               5 hours
        Reason:                 Repairs
        Effect:                 No air supply ventilation, cooling or
                                heating for 5 hours


Routine

        Building:               E23
        System:                 Air handler
        Date:                   6/8/95
        Day:                    Thursday
        Time:                   7:30 a.m. - 10:30 a.m.
        Duration:               3 hours
        Reason:                 Preventive maintenance
        Effect:                 No air supply ventilation or cooling
                                for 3 hours


Routine

        Building:               NW22
        System:                 Air handler
        Date:                   6/9/95
        Day:                    Friday
        Time:                   7:30 a.m. - 10:30 a.m.
        Duration:               3 hours
        Reason:                 Preventive maintenance
        Effect:                 No air supply ventilation or cooling
                                for 3 hours