B2 Power

daemon@ATHENA.MIT.EDU (John Chase)
Wed Mar 29 11:09:54 1995

To: MFILES%MITPPL.BITNET@mitvma.mit.edu
Cc: sdverify@MIT.EDU, hotline@MIT.EDU, dcns-cluster@MIT.EDU
Date: Wed, 29 Mar 1995 11:09:45 EST
From: John Chase <jchase@MIT.EDU>


        BLGD:           2
        SYSTEM:         ALL ELECTRIC POWER AND LIGHTING, EMERGENCY
                        POWER WILL BE ON
        DATE:           4/16/95
        DAY:            SUNDAY
        TIME:           12:00 AM - 6:00 AM
        DURATION:       SIX (6) HOURS
        REASON:         REPLACE 2400 VOLT FUSE HOLDERS ON MAIN SWITCH
                        FOR BLGD 2
        EFFECT:         NO POWER FOR SIX HOURS


 Hello Mary,
	i am removing the above shutdown from 'hold'. We have
	coordinated a plan at our end to handle our clusters...
	
	I will call Neil Thomlinson and tell him also.....

 John Chase