[27364] in Hotline Meeting
EMERGENCY SHUTDOWN OF POWER IN BUILDING 3
daemon@ATHENA.MIT.EDU (MFILES%MITPPL.BITNET@mitvma.mit.ed)
Wed Mar 15 16:07:59 1995
Date: Wed, 15 Mar 1995 16:07 EDT
From: MFILES%MITPPL.BITNET@mitvma.mit.edu
To: SHUTDOWNS@MIT.EDU
X-Envelope-To: SHUTDOWNS@MIT.EDU
X-Vms-To: IN%"SHUTDOWNS@MIT.EDU"
Earlier this afternoon a contractor had cut a cable which
resulted in the loss of electric power to the 3rd & 4th floors of
building 3. Quickly, temporary power was restored to those areas. In
order to fix the situation permanently and before a serious condition
occurs, we must shut down power to Building 3 all floors on the odd
side of the main corridor that runs between buildings 10 & 7.
Although we do not anticipate any problems, even if you have
nothing in that area it is very close to building 11 circuit breaker
wise. Best you should know.
This is an emergency shutdown and I apologize for any
inconvenience this may have caused.
Thank you.
Mary