We have already been notified about this, for the record:
To: SIRIANNI@MIT.EDU, RMOORE@MIT.EDU, MTAUB@MIT.EDU, CAVICCHI@MIT.EDU,
SMISCOWSKI%MITPPL@MITVMA.MIT.EDU, MTOBIN%MITPPL@MITVMA.MIT.EDU,
JFOLEY@MIT.EDU
Cc: LAMBERT@MITVMA.MIT.EDU, JIS@MIT.EDU
Subject: nov 19/20
Date: Mon, 7 Nov 94 13:58:28
From: wpwohlfa@MIT.EDU
LOOP 24A4 / 24B4
Saturday November 19th OUTAGE Bldg 1 & 3 - 7am to 7pm 12 hours
Also main group 1-8, 10,11 - 15 minutes between 7am & 8am
Sunday November 20th
44 - OUTAGE 7am to 8pm 13 hours
45 - OUTAGE, will HAVE EMERGENCY POWER ONLY - 7am to 8pm 13 hours
48 - 2 OUTAGEs 1)7am to 8am to install temp building generator
2)8pm to 9pm to remove temp building generator
PRESHUTDOWN WORK HAS BEEN INITIATED AND SHUTDOWN FORMS HAVE BEEN SUBMITTED.
GENERATOR RENTAL HAS BEEN SECURED FOR BLDG 48.
OTHER RELATED WORK - NEAR FUTURE - IN PLANNING STAGES ONLY:
1. outage to wind tunnel motor only ( in bldg 17)
2. outage to gas turbine motor only (in bldg 31)
3. outage to bldg 37 480v only ( to hookup 31 roof supply )
4. outage to bldg 31 480v only ( to cutover 31 roof feed )
5. outage to bldg 31 for 2400v primary cable replacement (low megger
readings) - will rent generator for secondary side power supply