[25026] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE:Shutdown

daemon@ATHENA.MIT.EDU (jjmorey@MIT.EDU)
Mon Oct 24 14:34:39 1994

From: jjmorey@MIT.EDU
To: op@MIT.EDU, hotline@MIT.EDU
Date: Mon, 24 Oct 1994 14:34:36 EDT


Hi Kim-

If it could say something like the following:

Barker clusters in bldg. 10-500 and 10-600
will be shutdown Wed Oct 26th night around 9pm
till Thurs 27th @ 7:45am.

and the following cluster will be shutdown starting
around 6am on Thurs 27th till 7:45am same day.

1-142
1-115
2-225
2-032
4-167
4-035
11-113
11-116

This is do to power being drop'd for the cogen project.

JJ

home help back first fref pref prev next nref lref last post