[24436] in Hotline Meeting

home help back first fref pref prev next nref lref last post

[VP] Cogen project

daemon@ATHENA.MIT.EDU (jjmorey@MIT.EDU)
Mon Sep 26 06:54:27 1994

From: jjmorey@MIT.EDU
To: shutdowns@MIT.EDU
Date: Mon, 26 Sep 1994 06:54:19 EDT


------- Forwarded Message

Received: from PACIFIC-CARRIER-ANNEX.MIT.EDU by po7.MIT.EDU (5.61/4.7) id AA23244; Fri, 23 Sep 94 16:40:37 EDT
Received: from MITVMA.MIT.EDU by MIT.EDU with SMTP
	id AA05382; Fri, 23 Sep 94 16:39:55 EDT
Received: from MITVMA.MIT.EDU by mitvma.mit.edu (IBM VM SMTP V2R2)
   with BSMTP id 1249; Fri, 23 Sep 94 16:38:58 EDT
Received: from MITPPL.BITNET (NJE origin MTOBIN@MITPPL) by MITVMA.MIT.EDU
 (LMail V1.2a/1.8a) with BSMTP id 3963; Fri, 23 Sep 1994 16:38:54 -0400
Received: from MITPPL.BITNET by MITPPL.BITNET (PMDF #12255) id
 <01HHGIIEH6QS8WWQD5@MITPPL.BITNET>; Fri, 23 Sep 1994 16:38 EDT
Date: Fri, 23 Sep 1994 16:38 EDT
From: MTOBIN%MITPPL.BITNET@mitvma.mit.edu
Subject: Cogeneration Switching
To: aac-aoquery@MIT.EDU, plant-managers@MIT.EDU, plant-sr-staff@MIT.EDU,
        jjmorey@MIT.EDU, jis@MIT.EDU, lippard@lippard.mit.edu, payne@MIT.EDU,
        mcgrath@mtl.mit.edu, bobcal@mitlns.mit.edu, benford@space.mit.edu,
        kgarceau@tower.lcs.mit.edu, lambert@mitvma.mit.edu, nolan@math.mit.edu
Message-Id: <01HHGIIEH6QS8WWQD5@MITPPL.BITNET>
X-Envelope-To: aac-aoquery@mit.edu, jis@mit.edu, jjmorey@mit.edu,
 payne@mit.edu, plant-managers@mit.edu, plant-sr-staff@mit.edu
X-Vms-To: 
 IN%"aac-aoquery@mit.edu",IN%"plant-managers@mit.edu",IN%"plant-sr-staff@mit.edu
   ",IN%"jjmorey@mit.edu",IN%"jis@mit.edu",IN%"lippard@lippard.mit.edu",IN%"payn
   e@mit.edu",IN%"mcgrath@mtl.mit.edu",IN%"bobcal@mitlns.mit.edu",IN%"benford@sp
   ace.mit.edu",IN%"kgarceau@tower.lcs.mit.edu",IN%"lambert@mitvma.mit.edu",IN%"
   jkay@mitppl@mitvma.mit.edu",IN%"nolan@math.mit.edu"
X-Vms-Cc: JKAY,MTOBIN

        We are notifying you of power switching that will be conducted
this afternoon relative to the Cogeneration Project.  The purpose of
this notification is to keep you informed as requested.  We anticipate
no power interruptions and nothing will be affected, nor should you see
any change in your services.  However, whenever there is power
switching, there is always a possibility of unanticipated power
interruptions.

        The actual switching schedule is from 6 am to 9 am, Tuesday,
9/27.  Again, this notification is for your information only.  The
buildings that are involved during this switch include:

        54, 56, 57, 16, 68, 66, E17, E18, E19

        Would you please circulate this message within your departments
as you feel is necessary.  If you have any questions concerning the
above, please feel free to call Bill Wohlfarth, x3-1741, or myself on
x3-1372.

        Thank you for your assistance.



                                        Mary Tobin, Supervisor
                                        Operations Center


------- End of Forwarded Message


home help back first fref pref prev next nref lref last post