[24398] in Hotline Meeting
[wpwohlfa@MIT.EDU: COGEN - OCT & NOV]
daemon@ATHENA.MIT.EDU (Cecilia d'Oliveira)
Fri Sep 23 09:31:50 1994
Date: Fri, 23 Sep 94 14:31:54
From: cec@MIT.EDU (Cecilia d'Oliveira)
To: network@MIT.EDU, op@MIT.EDU, hotline@MIT.EDU
------- Forwarded Message
Resent-Message-Id: <9409222158.AA09128@MIT.EDU>
Resent-Date: Thu, 22 Sep 94 17:56:42 EDT
Resent-From: "David F. Lambert" <LAMBERT@mitvma.mit.edu>
Resent-To: isdir@MIT.EDU
Return-Path: <wpwohlfa@MIT.EDU>
To: SIRIANNI@MIT.EDU, RMOORE@MIT.EDU, MTAUB@MIT.EDU, CAVICCHI@MIT.EDU,
SMISCOWSKI%MITPPL@mitvma.mit.edu, MTOBIN%MITPPL@mitvma.mit.edu
Cc: LAMBERT@mitvma.mit.edu, JIS@MIT.EDU
Subject: COGEN - OCT & NOV
Date: Thu, 22 Sep 94 14:19:24
From: wpwohlfa@MIT.EDU
Just FYI...
----------------------------Original message----------------------------
PRELIMINARY SCHEDULE - 2400 VOLT LOOP RECONFIGURATIONS
1. 24A2/24B2
Saturday October 15th OUTAGE 18 hours - Buildings: W15, W13 - (7am -11pm)
Possible 1 hour OUTAGE 1 hour - Buildings 44,45,48 - (bet 9pm-11pm)
Sunday October 16th - 16hours - switching only buildings (later)
2. 24A3/24B3
Saturday October 22nd - OUTAGE 18 hours - Building 20 - (7am -11pm)
Saturday October 29th - OUTAGE 18 hours - Building 12 - (7am-11pm)
Saturday November 5th - OUTAGE 18 hours - Building 31, 4-041, 2-017 (7am
-11pm)
Sunday November 6th - 12 hours - switching only buildings (later)
3. 24A4/24B4
Saturday November 19th - OUTAGE 18 hours - Bldgs:1-003,1-039,3-050 (7am -
11pm)
Sunday November 20th - OUTAGE 14 hours - Bldgs: 44,45,48 (7am-11pm)
THIS EFFORT WILL COMPLETE ALL CURRENTLY PLANNED LOOP
RECONFIGURATIONS/CUTOVERS. OTHER SWITCHING AND/OR OUTAGES MAY BE REQUIRED
LATER FOR G&W REPLACEMENT PROGRAM, OKONITE CABLE REPLACEMENT EFFORT AND
LOAD BALANCING.