Subject: Switching Power Back:
Date: Wed, 23 Mar 94 17:54:35 EST
I was paged by P.P. at approx. 4:40 pm and was told that power will be
switched back at 7:00pm this evening. The Bldg's involved were listed as
follows: 26,18,8,6B,14,50,62,13,9,31,35,37, and 7.
Carlton was contacted by Nina, from the Hayden Library area, asking if we
could shut here machines down. Carlton and I have taken care of this issue.
--Lou 3/23/94
This info was forwarded to shutdowns-
-Carlton 3/23
/* ---------- */
After being in Bldg 16. at approx 7:00pm when the power went out, I suspected
P.P. did not give me a complete list (pertaining to above). I have called
P.P. and asked what was happening. From what I could gather, they did not
anticipate the additional bldgs to loose power. These additional bldg's are
as follows: 2,10,12,12A,4,16,24,7A, & 70. Now from what I understand bdlg 11
has also lost power. The consultants in 11-115 said the lights went out, and
the systems went down. Another indication is that the 11-135 A/C unit alarms
were ringing. P.P. will look into this, but have no indication at their end
that this took place. All seems to be status quo at this moment.
--Lou 3/23/94
/* ---------- */