[20746] in Hotline Meeting
Power Shutdown 2-12-94
daemon@ATHENA.MIT.EDU (John Chase)
Mon Jan 24 11:09:07 1994
To: hotline@MIT.EDU
Date: Mon, 24 Jan 94 11:08:20 EST
From: John Chase <jchase@MIT.EDU>
------- Forwarded Message
Received: from MIT.MIT.EDU by po6.MIT.EDU (5.61/4.7) id AA21801; Mon, 24 Jan 94 10:01:10 EST
Received: from BIGREDONE.MIT.EDU by MIT.EDU with SMTP
id AA12974; Mon, 24 Jan 94 10:00:59 EST
Message-Id: <9401241500.AA12974@MIT.EDU>
Date: Mon, 24 Jan 94 10:03:21
From: burke@MIT.EDU (Jerry Burke)
To: dcns-cluster@MIT.EDU
Subject: electrical power and emergency outages
Cc: dcns-support@MIT.EDU, ops@MIT.EDU, network@MIT.EDU
February 12, 7am to 7:15am
affects lots of buildings
1,2,3,4,5,6,7,7a,8,9,10,11,12,13,14,18,24,26,33,34,35,37,38,39,50,54,56,
62,64,66,e1,e2,e3,e18.
February 10, Thursday 7am to 7:30am
electrical power -- bldg. 8, 12, 24, 12a
February 12 Sauturday 18 hours
Electrical power -- N9/N10 44, 45, 48
February 13 Sunday 20 hours
Bldgs. 44, 45, 48, N9, N10
All theses power shutdowns are part of the co-genaration projects.
Copies of the shutdown request have been given to netops and
dcns-clusters. IF you would like to see a copy let me know.
Jerry