[20105] in Hotline Meeting
2-225 retiled
daemon@ATHENA.MIT.EDU (jjmorey@MIT.EDU)
Tue Dec 7 08:30:02 1993
From: jjmorey@MIT.EDU
To: dcns-cluster@MIT.EDU
Cc: op@MIT.EDU, hotline@MIT.EDU
Date: Tue, 07 Dec 93 08:29:49 EST
Hi All-
2-225 will be getting retiled on 12-21-93 Tues starting 8am.
Ops, can we get an MOTD Thurs 9th in the afternoon, thanks.
Lou, you will need to shutdown the cluster Monday night say
around 9pm. If you could disable the code, queues,
shutdown the systems and unplug as much as possible, thanks.
JC and I will be in around 6am Tues to start removing equipment
from rm and should be done before 8am.
Tony should be done around 4pm Tues afternoon, Carlton and Lou
should be able to start moving equipment back in and cluster
should reopen around 7pm.
If there are any questions/problems/suggestions please bring
them up at CSR meeting Thurs or earlier.
Thanks
JJ