Bldg 46 - ALl - Medium and Low Pressure Steam Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Tue Mar 29 08:40:41 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <whomeyer@mit.edu>, <sinanig@mit.edu>, <msmalley@mit.edu>
Date: Tue, 29 Mar 2016 08:40:28 -0400
Message-ID: <6FB221164F31437694F2A80D74C1D6D0@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following medium and low pressure steam shutdown request for bldg. 46 - all, on Saturday, April 2, 2016, from 6:00am thru 4:00pm, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Amy Chamberlain-Chioccola
Comprehensive Stewardship Group
Dept. of Facilities
x5-4164
Type: Normal
Date: April 2, 2016
Day: Saturday
Time: 6:00am - 4:00pm
Building(s): 46
Room(s): All
System: Medium and Low Pressure Steam
Duration: 10 Hours Max
Reason:
We request a bldg 46-2201u/m med/low pressure steam shutdown from 6 AM to 4 PM on Saturday, April 2nd, 2016 for Enterprise Equip0ment Co to remove a check valve, install a gate valve, and add a trap on the condensate returns from the new clean steam generator as part of the bldg 46 new clean steam generator project by Acella Construction (Rob Lorscheider 781-727-8835). Affected are the clean steam generators and steam to the bldg's lab process hot water heaters. Gerhard Sinani 4-1705 and Thanh Nguyen 4-6911 are the MIT project managers.
Effect:
Loss of medium and low pressure steam and hot lab process water for the duration of the shutdown.