[186152] in Hotline Meeting
Bldg. 76 - Reverse Osmosis Pumps, Power Panel R2B Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Wed Mar 9 14:57:02 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <silask@mit.edu>
Date: Wed, 9 Mar 2016 14:57:01 -0500
Message-ID: <F153FE27F3084C88B2141B1DEA279546@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following power panel R2B shutdown request for Bldg. 76 - RO Pumps, on Tuesday, March 15, 2016, 11:30pm - 1:30am on Wednesday, March 16, 2016, is for your information and response. Any questions, please contact Silas Keenan, x4-7230.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: March 15, 2016
Day: Tuesday
Time: 11:30pm (Tues.) - 1:30am (Wed.)
Building(s): 76
Room(s): Reverse osmosis pumps
System: Power Panel R2B
Duration: 2 hours
Reason:
to install a new breaker for new RO Pump
Effect:
Loss of power to the RO pumps, pure water, and de-ionized water for the duration of the shutdown.