Approved Bldg. E51 - Entire Building Fire Protection Water Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Thu Mar 3 11:42:07 2016

From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <wjlombar@mit.edu>, <keb@mit.edu>
Date: Thu, 3 Mar 2016 11:42:14 -0500
Message-ID: <B857AF2507304F41BC6BFC42CDDCF69C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Protection Water shutdown notification for Bldg. E51 - Entire Building on Saturday, March 5, 2016 from 6am to 10am is for your information. No response required to this notification. Any question please contact Billy Homeyer @ 8-0432.

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Bill Lombard
Repair & Maintenance
617-324-7705


Type: Normal
Date: March 5, 2016
Day: Saturday
Time: 6am - 10am
Building(s): E51
Room(s): Entire Building
System: Fire Protection Water
Duration: 4 hours
Reason: 
To Install 1st Floor Sprinkler Zone Control Valve Assembly (Tamper/Waterflow/Test Drain)

Effect: 
Loss of Fire Protection Water for duration of the shutdown