Approved Bldg. 16, & 26 - Entire Buildings Fire Alarm System (w/*Live Audible Testing on 3/3 from 6am to 7am, & 3/4 from 6:30am to 7:30am*) Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Tue Mar 1 08:33:21 2016

From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <wjlombar@mit.edu>, <acorson@mit.edu>
Date: Tue, 1 Mar 2016 08:33:11 -0500
Message-ID: <C3A79FB3A3DD42A78F4D40EE4A91AF16@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Alarm System (w/*Live Audible Testing on 3/3 from 6am to 7am, & 3/4 from 6:30am to 7:30am*) shutdown notification for Bldg. 16, & 26 - Entire Buildings on Wednesday, March 2, 2016 from 6am to 4pm, Thursday, March 3, 2016 from 6am to 7am, and Friday, March 4, 2016 from 6:30am to 8am is for your information. No response required to this notification. Any question please contact Billy Homeyer @ 8-0432.

Please note Bldg. 26 classes begin at 8 AM. 

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Bill Lombard
Repair & Maintenance
617-324-7705


Type: Normal
Date: March 2, 2016
Day: Wednesday
Time: 3/2 - 6am to 4pm, 3/3 - 6am to 7am, 3/3 - 6:30am to 8am
Building(s): 16, & 26
Room(s): Entire Buildings
System: Fire Alarm System (w/*Live Audible Testing on 3/3 from 6am to 7am, & 3/4 from 6:30am to 7:30am*)
Duration: 3/2 - 10 hours, 3/3 - 1 hour, 3/4 - 1.5 hours
Reason: 
For Smoke Detector, and Pull Station Relocation to Make Way for Steam Piping, and Live Testing

Effect: 
Loss of Fire Alarm System for duration of the shutdown