[186086] in Hotline Meeting
Approved bldg 13-basement smoke detector shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Thu Feb 25 13:47:06 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <ksemerj@mit.edu>, <shutdowns@mit.edu>, <whomeyer@mit.edu>,
<rm-shutdown@mit.edu>, <safety@mit.edu>, <operators@mit.edu>,
<csc@mit.edu>, <rm-fire-prot-team@mit.edu>, <ksemerj@mit.edu>,
<mderoche@mit.edu>, <mkefalis@mit.edu>
Date: Thu, 25 Feb 2016 13:47:12 -0500
Message-ID: <7D5532F52FA0430FA4D5C818EFBC1956@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector shutdown for bldg. 13-basement starting on Wednesday March 2nd thru Friday March 18th, 2016 from 6am to 4pm is for your information. No response is required for this notification. Any questions, please contact Billy Homeyer 8-0432 / Karen Semerjian 3-6217. Thank you.
Type: Normal
Date: March 2, 2016
Day: Wednesday
Time: 6am to 4pm
Building(s): 13
Room(s): Basement
System: Smoke detectors
Duration: 10 hours
Reason:
General construction-related activities for hot work associated with replacement of AH1, AH2 and AH3 chilled water valves
Effect:
Loss of smoke detectors for duration of shutdown