Bldg 2 - Bsmnt - Fire Protection Water Shutdown and w/*Live Audible Testing Request
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Wed Feb 24 09:14:06 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <mdeluga@mit.edu>, <whomeyer@mit.edu>, <sgilliga@mit.edu>
Date: Wed, 24 Feb 2016 09:14:19 -0500
Message-ID: <34A265AD6190468C87C262AC874AC7E8@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire protection water shutdown - basement and intermittent *live audible testing - all, request for Bldg. 2 on Monday, February 29, 2016, and Tuesday, March 1, 2016, from 6:00am - 2:00pm, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Amy Chamberlain
Comprehensive Stewardship Group
Dept. of Facilities
x5-4164
Type: Normal
Date: February 29, 2016
Day: Monday
Time: 6:00am - 2:00pm each day
Building(s): 2
Room(s): Bsmnt/All
System: Fire Protection Water w/*Live Audible Testing
Duration: 8 Hours each day
Reason:
Project 11119 - Math renovation - 2
02/23/2016 14:52:29 EST Karen E Semerjian (KSEMERJ) Phone 617 253-6217
We request a sprinkler shutdown in bldg 2-basment from 6 AM to 2 PM on Monday, February 29th for replacing main water flow switch in 2-044 mech room; and from 6 AM to 7 AM on Tuesday March 1st, 2016, we will conduct intermittent brief live testing in order to set timing and test the new water flow switch associated with the bldg 2 Math renovation project by Bond Brothers (Ben Ross 617-872-9129). Marty Deluga 4-5081 is the MIT project manager on behalf of Billy Homeyer.
Effect:
Loss of fire protection water w/*intermittent live audible testing for the duration of the shutdown.