[185898] in Hotline Meeting
Approved bldg NW22-1st floor and AH2 duct smokes smoke detector shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Tue Feb 2 09:08:13 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <ksemerj@mit.edu>, <shutdowns@mit.edu>, <whomeyer@mit.edu>,
<rm-shutdown@mit.edu>, <safety@mit.edu>, <operators@mit.edu>,
<csc@mit.edu>, <rm-fire-prot-team@mit.edu>, <ksemerj@mit.edu>,
<mderoche@mit.edu>, <biss@mit.edu>
Date: Tue, 2 Feb 2016 09:08:41 -0500
Message-ID: <1E904818BD6642C9A12CCA26020C101E@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector and duct smokes detector for bldg NW22-1st fl and AH2 duct smokes on Tuesday, Wednesday and Thursday, February 2nd, 3rd and 4th, 2016 from 6am-2pm is for your information. No response is required for this notification. Any questions please contact Billy Homeyer 8-0432 / Karen Semerjian 3-6217
Type: Normal
Date: February 2, 2016
Day: Tuesday
Time: 6am-2pm
Building(s): NW22
Room(s): 1st floor /room 161 / AH2 duct smokes
System: Smoke Detectors and Duct smokes
Duration: 8 hours
Reason:
For construction dust and all general construction-related activities while installing HEPA air filtration systems
Effect:
Loss of smoke detectors for duration of shutdown