Approved Bldg. W20 - 5th Floor Normal Power 120 Volt Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Mon Feb 1 12:00:15 2016

From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <wjlombar@mit.edu>, <gsailba@mit.edu>
Date: Mon, 1 Feb 2016 12:00:20 -0500
Message-ID: <BFD3BA3B51D840B3810C97EE5E23F1F8@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal Power 120 Volt shutdown notification for Bldg. W20 - 5th Floor on Wednesday, February 3, 2016 from 6am to 8am is for your information. No response required to this notification. Any question please contact Mike DeRoche @ 617-866-0290.

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Bill Lombard
Repair & Maintenance
617-324-7705


Type: Normal
Date: February 3, 2016
Day: Wednesday
Time: 6am - 8am
Building(s): W20
Room(s): 5th Floor
System: Normal Power 120 Volt 
Duration: 2 hours
Reason: 
To Tie In Temporary Power

Effect: 
Loss of Normal Power 120 Volt for duration of the shutdown