Approved bldg 13-basement smoke detector shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Fri Jan 29 13:36:40 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <ksemerj@mit.edu>, <shutdowns@mit.edu>, <whomeyer@mit.edu>,
<rm-shutdown@mit.edu>, <safety@mit.edu>, <operators@mit.edu>,
<csc@mit.edu>, <rm-fire-prot-team@mit.edu>, <ksemerj@mit.edu>,
<mderoche@mit.edu>, <jmannion@mit.edu>, <acorson@mit.edu>
Date: Fri, 29 Jan 2016 13:37:09 -0500
Message-ID: <A9CAF276877B45F59B8E4B3BE0BAFF0D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector shutdown for bldg 13 -basement on Tuesday, February 2nd thru Thursday, February 4th, 2016 from 5am-3pm is for your information. No response is required for this notification. Any questions please contact Billy Homeyer 8-0432 / Karen Semerjian 3-6217
Thank you
Karen Semerjian
Facilities - CC Project Mgmt
617-253-6217
Type: Normal
Date: February 2, 2016
Day: Tuesday
Time: 5am-3pm
Building(s): 13
Room(s): Basement
System: Smoke Detectors
Duration: 10 hours
Reason:
For general construction-related activities during welding and steam start-up
Effect:
Loss of smoke detectors for duration of shutdown