[185865] in Hotline Meeting
Approved bldg 4 - bsmt south smoke detector shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Thu Jan 28 11:47:36 2016
From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <ksemerj@mit.edu>, <shutdowns@mit.edu>, <whomeyer@mit.edu>,
<rm-shutdown@mit.edu>, <safety@mit.edu>, <operators@mit.edu>,
<csc@mit.edu>, <rm-fire-prot-team@mit.edu>, <ksemerj@mit.edu>,
<mderoche@mit.edu>, <jmcgilvray@acellaconstruction.com>, <keb@mit.edu>,
<dunnc@mit.edu>
Date: Thu, 28 Jan 2016 11:48:06 -0500
Message-ID: <733D8DCE9470482F938D8D1C48470EBD@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector shutdown for bldg 4-bsmt south and corridor starting Monday, February 1st thru Friday, Feburary 26th, 2016 (regular work days) from 6am-2pm is for your information. No response is required for this notification. Any questions, please contact Billy Homeyer 8-0432/ Karen Semerjian 3-6217
Type: Normal
Date: February 1, 2016
Day: Monday
Time: 6am-2pm
Building(s): 4
Room(s): Basement south & corridor
System: Smoke Detector
Duration: 8 hours
Reason:
For construction dust and all general construction-related activities
Effect:
Loss of smoke detectors for duration of shutdown
This message was sent the following recipients: graham@mit.edu; abm@mit.edu; avall@mit.edu; myersm@MIT.EDU; mariusz@mit.edu; swade@mit.edu; rjwilk@mit.edu; Bales@mit.edu; acalogge@mit.edu; slipnosk@mit.edu; sharonp@mit.edu; rtdavis@mit.edu; jarrod@mit.edu; rm-mcs@mit.edu; cust-staff@mit.edu; colins@mit.edu; mbj@mit.edu; wangal@mit.edu; pbhouk@gmail.com; angelita@mit.edu; ashervan@mit.edu; tarky@mit.edu; mottley@mit.edu; carleton@mit.edu; cubstead@MIT.EDU; cljames@mit.edu; cmodica@mit.edu; schedules@mit.edu; scottide@MIT.EDU; heatherg@mit.edu;