Bldg. 18 - All, Fire Alarm Shutdown and *Live Audible Testing Request

daemon@ATHENA.MIT.EDU (shutdown-response@mit.edu)
Wed Jan 27 10:15:29 2016

From: shutdown-response@mit.edu
To: <undisclosed_recipients@mit.edu>
Cc: <whomeyer@mit.edu>, <sgilliga@mit.edu>
Date: Wed, 27 Jan 2016 10:15:58 -0500
Message-ID: <AD326928B1814FDC98FB11653B2BB4C4@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following fire alarm shutdown and *live audible testing request for Bldg. 18 - all, on Thursday, January 28, 2016, and Friday, January 29, 2016, from 6:00am - 2:00pm, and Monday, February 1, 2016, from 6:00am - 10:00am, with *live testing on Friday, January 29, 2016 and Monday, February 1, 2016 from 6:00am - 8:00am, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Amy Chamberlain-Chioccola
Comprehensive Stewardship Group
Dept. of Facilities
x5-4164


Type: Normal
Date: January 28, 2016
Day: Thursday
Time: 6-2(Thurs, Fri)/ 6-10(Mon)/*live testing 6-8(Fri, Mon)
Building(s): 18
Room(s): All
System: Fire Alarm w/*Live Audible Testing
Duration: 8 Hours/8 Hours/4 Hours/*live testing 2 Hours
Reason: 
We request bldg 18 fire alarm shutdowns on Thursday, Friday and Monday, January 28th, 29th and February 1st, 2016 as follows;
from 6 AM to 2 PM on Thurs/Fri, Jan 28th/29th for Aldon Electric (Roger Thibault 617-908-0677/Keith Dube 978-857-7414) and Simplex (Rich Perron 781-603-7799) to clear 3rd party punchlist item and rework subbsmt and 1st floor annunciator panel LED's; and from 6 AM to 10 AM on Mon, Feb 1st to conduct 3rd party testing, which will be witnessed by JMBCo (Wayne Maginnis 617-212-2059). We will conduct *live audible testing of the bldg 18 fire alarm system between 6 and 8 AM on Fri 1/29 and Mon 2/1* followed by silent testing until 10 AM (or completion) and as part of the 18-083/087 Prof Schlau-Cohen lab renovation project by JLL (Niles Carter 617-590-0734/Steve Pizzuto 617-212-0519). 

Drew Murphy 4-7856 and Joe Collins 3-3621 are the MIT project managers.


Effect: 
Loss of fire alarms for the duration of the shutdown and *live audible testing.