[185845] in Hotline Meeting
Approved: Bldg.W7 - Entire Building - Domestic Hot Water Shutdown
daemon@ATHENA.MIT.EDU (Nicole McKenna)
Mon Jan 25 13:22:39 2016
From: Nicole McKenna <nmckenna@mit.edu>
To: Michael Myers <myersm@mit.edu>,
OPS RM Campus Services West
<IMCEAEX-_O=MIT_OU=PLANT_cn=Recipients_cn=RM-WCS@exchange.mit.edu>,
"Stephen
R Charles" <src@mit.edu>, Dennis Collins <colins@mit.edu>,
hmgr
<hmgr@mit.edu>, Charlene M McLaughlin <cmcclaug@mit.edu>,
Christopher Nolan
<kcn@mit.edu>, shutdowns <shutdowns@mit.edu>,
rm-shutdown
<rm-shutdown@mit.edu>, dof-ehs <dof-ehs@mit.edu>,
cp-command
<cp-command@mit.edu>, safety <safety@mit.edu>,
"operators@plant.mit.edu"
<operators@PLANT.MIT.EDU>,
DOF Customer Service Center
<IMCEAEX-_O=MIT_OU=PLANT_cn=Recipients_cn=dof-csc@exchange.mit.edu>,
"Ops
Custodial Admin & Support Staff"
<IMCEAEX-_O=MIT_OU=PLANT_cn=Recipients_cn=cust-staff@exchange.mit.edu>,
plumbing <plumbing@mit.edu>
CC: David Hingston <dhingsto@PLANT.MIT.EDU>
Date: Mon, 25 Jan 2016 18:22:34 +0000
Message-ID: <1C902845F98D594DB6C9EF3C1FCA5A9E28B6758D@OC11EXPO33.exchange.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved shutdown notification for building W7 Domestic Hot Water on Tuesday, January 26, 2016 is for your information. No response is required to this notification. Any question please contact Dave Hingston, ext. 4-4548.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Nicole McKenna
Repair & Maintenance
617-324-7705
Type: Normal
Date: January 26, 2016
Day: Tuesday
Time: 10:00 am - 2:00 pm
Building(s): W7
Room(s): Entire Building
System: Domestic Hot Water
Duration: 4 Hours
Reason:
Old piping water supply needs to be replaced
Effect:
loss of domestic hot water for duration of shutdown