W91 Chilled Water Shutdown

daemon@ATHENA.MIT.EDU (Kevin Gedrich)
Mon Sep 24 14:12:10 1990

Date:         Mon, 24 Sep 90 14:09:28 EDT
Reply-To: Kevin Gedrich <GEDRICH%MITVMC.BITNET@mitvma.mit.edu>
From: Kevin Gedrich <GEDRICH%MITVMC.BITNET@mitvma.mit.edu>
To: Athena Consultant <CFYI@ATHENA.MIT.EDU>,

Please post where appropriate.....Kevin Gedrich

----------------------------Original message----------------------------
PM has been scheduled for BOTH the W91 chiller towers on Saturday,
10/6/90.  The PM is estimated to take 8-10 hours (we really
believe it won't take that long though).  This will definitely
require shutdowns of the Cray, MITVMA & MITVMC.  Depending on
Physical Plant's requirements we will probably not have A/C
either.  The lack of A/C will probably require shutdowns of
other equipment too (Vax's, peripherals, etc.).  I think we
should all plan for a complete building shutdown just
to play it safe.  Physical Plant will start at 8am.  The Cray &
IBM mainframes should be shutdown by 8am.


I appreciate everyone's cooperation for this required maintenance.
Thanks.                                                            -Dave