Bldg. 54- 5th fl Chilled Water Shutdown (bldg. 54- 529 Computer rm) (Process/HVAC Chilled Water)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Aug 19 08:51:31 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <jmannion@plant.mit.edu>
Date: Mon, 19 Aug 2013 08:51:27 -0400
Message-ID: <F9D8D667454840CFB268E0C4F4739F8B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Chilled Water (Process/HVAC Chilled Water) shutdown is for bldg. 54 - 5th fl. (bldg. 54 - 529 computer rm) on Wednesday, August 21, 2013 from 7:00am - 11:00am is for your information and approval. Any questions please contact Jack Mannion 617-592-4547.


Would you please let us know if this does or does not have your approval.

Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: August 21, 2013
Day: Wednesday
Time: 7:00am - 11:00am
Building(s): 54
Room(s): 5th fl. 511A, 529 computer rm
System: chilled water
Duration: 4 hrs  7:00am - 11:00am
Reason: 
This is for bldg. 54- 511 fan coil unit chilled water tie in.   This is for bldg. 54- 5th fl as well as rm 529 - computer room. Process/HVAC chilled water.

Effect: 
Loss of chilled water for the duration of this shutdown.