[171513] in Hotline Meeting
Bldg. 9-All Fire Alarm, elevators (w/*live audible testing from 6AM to 7:30AM)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Aug 15 09:20:12 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <pjmurphy@MIT.EDU>
Date: Thu, 15 Aug 2013 09:20:07 -0400
Message-ID: <303CF97108DA45AC952DE8683F67B608@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Alarm, elevators (w/*live audible testing from 6AM to 7:30AM) shutdown is for bldg. 9 - All on Friday, August 16, 2013 from 6:00am - 9:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 16, 2013
Day: Friday
Time: 6:00am - 9:00am
Building(s): 9
Room(s): all
System: fire alarm, elevators
Duration: 6:00am - 9:00am
Reason:
We request a bldg 9-all fire alarm shutdown from 6 AM to 9 AM on Friday morning, August 16th, 2013 to conduct *live audible 3rd party testing of the bldg 9 fire alarm system from 6 AM to 7:30 AM* followed by silent testing and inspection until 9 AM and to be witnessed by J. & M. Brown Co. (Wayne Maginnis 617-212-2059) and with MacNichol Electric (Tom Durant 978-930-6001) as required and related to the bldg 9 elevator upgrade project by Commodore Builders (Ralph D'Antonio 617-719-4682). Paul Murphy 4-6163 is the MIT project manager.
Effect:
Loss of fire alarms and elevators for the duration of this shutdown.