[171503] in Hotline Meeting
Approved: Bldg. E52 - All High/Medium/Low Pressure Steam, Chilled
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Wed Aug 14 14:32:53 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "asteward@mit.edu" <asteward@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
"sdimond@mit.edu" <sdimond@mit.edu>,
"lmorales@mit.edu" <lmorales@mit.edu>,
"bshuster@MIT.EDU" <bshuster@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
"wangal@mit.edu" <wangal@mit.edu>, Michael Smith
<masmith@mit.edu>,
"mdimauro@MIT.EDU" <mdimauro@mit.edu>,
"MIT Schedules
Office" <schedules@mit.edu>,
"lhill@mit.edu" <lhill@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>,
"ksemerj@mit.edu" <ksemerj@mit.edu>,
"mmcorrei@mit.edu"
<mmcorrei@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS
<dof-ehs@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "rquade@mit.edu" <rquade@mit.edu>
Date: Wed, 14 Aug 2013 14:32:46 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C69DEBBC@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved High/Medium/Low Pressure Steam, Chilled Water Shutdown is for bldg. E52- All on Thursday, August 15, 2013 at 6:00am until further notice is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 15, 2013
Day: Thursday
Time: 6:00am - until further notice
Building(s): E52
Room(s): all
System: high/medium/low pressure steam, chilled water
Duration: 8/15 - 6:00am - until further notice - project demo phase
Reason:
We request bldg E52-all HP/MP/LP steam and chilled water shutdowns, (HP steam for E52 fed from E53, chw shutdown in E52 bsmt), at 6 AM on Thursday, August 15th to support the demo phase of the bldg E52 bldg renovation project by Suffolk Construction (Ralph Morse 508-326-7614). Rich Quade 4-3338 and Sonia Richards 4-2480 are the MIT project managers.
Effect:
Loss of high/medium/low pressure steam, chilled water for the duration of the project.