[171479] in Hotline Meeting
Bldg. W20 - All Domestic Hot and Cold Water Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Aug 13 14:59:37 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sudy@MIT.EDU>
Date: Tue, 13 Aug 2013 14:59:20 -0400
Message-ID: <94A057B7E373412F93A9A61F6EAC3B49@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Domestic Hot and Cold Water Shutdown is for bldg. W20 - All on Thursday, August 15, 2013 from 4:00am til 6:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please review and let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 15, 2013
Day: Thursday
Time: 4:00am - 6:00am
Building(s): W20
Room(s): All
System: hot/cold domestic water
Duration: 4:00am - 6:00am
Reason:
We request a bldg W20-all domestic h/c water shutdown from 4 AM to 6 AM on Thursday morning, August 15th, 2013 for tying in domestic water to the new 019 kitchen grease intercept system as part of the catering kitchen renovation project by Elaine Construction (Robin Lorscheider 781-727-8835). Sudy Nally 8-8010 is the MIT project manager.
MIT plumbing will begin draining at 4 AM and the system will be filled/fully operational at 6 AM.
Effect:
Loss of hot and cold domestic water for the duration of this shutdown.