*Extended and Modified - Bldg. 32 - Stairwell Pressurization -

daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri Aug 9 12:24:21 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "mwf@mit.edu" <mwf@mit.edu>, "liscott@mit.edu" <liscott@mit.edu>,
        "tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
        "jackc@csail.mit.edu" <jackc@csail.mit.edu>,
        "steverug@CSAIL.MIT.EDU"
	<steverug@csail.mit.edu>,
        "isabell@mit.edu" <isabell@mit.edu>, "sbleeb@mit.edu" <sbleeb@mit.edu>,
        Michael Fahie <mfahie@plant.mit.edu>,
        "OPS RM Campus Services Main" <rm-mcs@mit.edu>,
        "Martin O'Brien"
	<mobrien@plant.mit.edu>,
        "Stata-Custodial@mit.edu" <Stata-Custodial@mit.edu>,
        Ops CSG All <csg-all@mit.edu>, "dwright@MIT.EDU" <dwright@mit.edu>,
        "stata-desk@mit.edu" <stata-desk@mit.edu>,
        "rosko@mit.edu" <rosko@mit.edu>, Michael Smith <masmith@mit.edu>,
        "edel@mit.edu" <edel@mit.edu>, "shanlon@mit.edu" <shanlon@mit.edu>,
        "lrbrutti@mit.edu" <lrbrutti@mit.edu>, "rcruz@mit.edu" <rcruz@mit.edu>,
        "aneely@mit.edu" <aneely@mit.edu>,
        "MIT
 Schedules Office" <schedules@mit.edu>,
        "kdonaher@mit.edu" <kdonaher@mit.edu>,
        "kasabula@mit.edu" <kasabula@mit.edu>,
        "rpittari@mit.edu" <rpittari@mit.edu>,
        "ksimons@mit.edu" <ksimons@mit.edu>,
        "rwong@brighthorizons.com"
	<rwong@brighthorizons.com>,
        "worklife@mit.edu" <worklife@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "ksemerj@mit.edu" <ksemerj@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@mit.edu>
CC: "kdiggans@mit.edu" <kdiggans@mit.edu>
Date: Fri, 9 Aug 2013 12:24:12 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C687EFF8@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following *extended and modified supply fans 9 & 9A and exhaust fan 2 shutdown request for Bldg. 32 - stairwell pressurization on Wednesday, August 21, 2013, 6:00am - 4:00pm, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilties
x3-6381

Type: Normal
Date: August 21, 2013
Day: Wednesday
Time: 6:00am- 4:00pm
Building(s): 32
Room(s): Stairwell Pressurization
System: Supply Fans 9 & 9A and Exhaust Fan 2
Duration: 10 hours
Reason: 
Original: We request a bldg 32-SF9,SF9A (stairwell pressurization fans) shutdown (NOTE: normally off; will cause brief fire alarm trouble when bumped for rotation) from 6 AM to 4 PM on Thursday, July 25th, 2013 for rooftop relocation as part of the 32-roof repair project by Consigli Construction (Carlin Grenier 508-458-0590).  Keith Diggans 4-6174 is the MIT project manager on behalf of Billy Homeyer.

*Extended and Modified - We would like to modify and extend the bldg 32G -SF9,SF9A and to also include EF2 from 6 AM to 4 PM on Wednesday, August 21st, 2013 to install permanent power to equipment and disconnect and remove the old temporary power as part of the bldg 32-roof repair project by Consigli Construction (Carlin Grenier 508-509-2935). Keith Diggans 4-6174 is the MIT project manager on behalf of Billy Homeyer.

Effect: 
Loss of supply ventilation for the duration of the shutdown.