[171416] in Hotline Meeting
Bldg. 18 - 3rd Floor Only - Lab Process Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Aug 9 11:33:04 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <ajsilva@MIT.EDU>, <mgodding@MIT.EDU>
Date: Fri, 9 Aug 2013 11:33:01 -0400
Message-ID: <6E23CD94DADE4C1595B667BFA62801C8@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following lab process chilled water shutdown request for Bldg. 18 - 3rd Floor Only, on Wednesday, August 14, 2013, 7:00am - 1:00pm, one shaft at a time, two hours per shaft, three shafts total, is for your information and response. Any questions, please contact Joe Silva, x3-1602.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: August 14, 2013
Day: Wednesday
Time: 7:00am - 1:00pm
Building(s): 18
Room(s): 3rd Floor Only
System: Lab Process Chilled Water
Duration: 6 hours - one shaft at a time, two hours per shaft, three shafts total
Reason:
to install a new shutoff valve and strainer regulators
Effect:
Loss of lab process chilled water for the duration of each 2 hour shaft shutdown.