[171410] in Hotline Meeting
Bldg.W79 - 1st Floor, Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Aug 9 08:55:52 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <cgilbert@MIT.EDU>, <mwhelan@mt.edu>
Date: Fri, 9 Aug 2013 08:55:42 -0400
Message-ID: <346B62611FE841A594B23EFC6F48BE10@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smokes detector shutdown notification for Bldg.W79 - 1st floor on Monday, August 12, 2013 thru Wednesday, August 14, 2013, from 8:00am-4:00pm, is for your information. No response is required to this notification. Any questions please contact Marsha Whelan, X. -4-4324.
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Chris Gilbert
Operations Center
Type: Normal
Date: August 12, 2013
Day: Monday
Time: 8:00am-4:00pm
Building(s): W79
Room(s): 1st floor
System: Smoke detectors
Duration: 8 hours each day
Reason:
installation of dishwasher in Dish Room.
Effect:
Loss of smoke detector coverage in area during duration of shutdown.