[171272] in Hotline Meeting
Bldg. WN12- All Domestic Cold Water Shutdown (potable)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Aug 5 09:09:34 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <jcombs@MIT.EDU>
Date: Mon, 5 Aug 2013 09:08:50 -0400
Message-ID: <BD8F8735ACD44DAF8718A3741383A61C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Domestic Cold Water (potable) Shutdown is on Wednesday, August 7, 2013 from 6:00am - 8:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 7, 2013
Day: Wednesday
Time: 6:00am - 8:00am
Building(s): NW12
Room(s): all
System: domestic cold water
Duration: 6:00am - 8:00am
Reason:
We request a bldg NW12-all domestic cold water (potable) shutdown from 6 AM to 8 AM on Wednesday, August 7th, 2013 to install a 2" line that feeds the new water heater for tempered water for emergency shower as part of the NW12 lab exhaust hood project by Acella Construction (Dennis Tellier 781-831-4497). Jennifer Combs 3-7671 on behalf of Billy Homeyer.
Effect:
Loss of domestic cold water for the duration of this shutdown.